Peacock Theater, L A. Live
<aside>
</aside>
| Monday | 6/22 | Union crews start, Tent Build, Truss Build, Power Drop, Fencing install |
|---|---|---|
| Tuesday | 6/23 | Production Office set-up, truss & tent builds continue |
| Wednesday | 6/24 | Red Carpet Install Begins, Drapery in Red Carpet & VIP Area |
| Thursday | 6/25 | Decking and scenic wall installation, Lighting Install Begins |
| Friday | 6/26 | Decor and graphic installations continue, hedges delivered, Press Room Set-up begins, stanchion walls installed |
| Saturday | 6/27 | Decor and graphic installations continue, hedge placement continues, stanchion walls installed, florals placed |
| Sunday | 6/28 | SHOW DAY |
| Monday | 6/29 | Scenic, carpet and truss strike, Release parts of CHC 6am for Anime festival |
| Tuesday | 6/30 | Final Equipment pick-ups |